Dock, Ramp & Float Maintenance Above the Water
Decking, railings, ladders, cleats, hardware, and non-slip surfaces on a private dock, gangway, or float. Read the permit paragraph before you call, because it decides whether I can touch your dock at all.
- Licensed & bonded
- WA L&I #SANJUJI741OT
- Insured
- Locally owned in Friday Harbor
Start with the line, because on this one it is the most useful thing on the page. What I do on a dock is carpentry and hardware above the water: deck boards, railings, ladders, cleats, chocks, hinge and fastener replacement, non-slip surfaces, and a written seasonal inspection. What I do not do is anything in the water or below the high water line. No pilings. No flotation, no float tubs, no anchoring or chain and cable work. No ramp or gangway relocation, no bulkheads, no beach or bank work, no barge-based work. That is marine contracting, it is permitted work, and it belongs to people who do it for a living.
Now the permits, and I am going to be blunt rather than reassuring, because getting this wrong is expensive for the owner and not for the contractor. Washington’s Department of Fish and Wildlife lists docks, piers, ramps, floats, boathouses, and buoys as project types needing a Hydraulic Project Approval for new work, repair, modification, and replacement, and WDFW states in the same place that the requirement can reach projects above the ordinary high water line. San Juan County is equally direct in its own guidance: building a new dock usually requires a shoreline permit, reconfiguring one may require a permit or a revision to an existing one, and repairing an existing dock usually requires approval of an exemption from a shoreline permit — which is a written county approval, not a shrug. Shoreline rules apply to the landward two hundred feet of the ordinary high water mark as well as the aquatic area itself.
So the working rule at my end is simple. Before I do anything on a dock, ramp, or float, I want to see the current approvals for the work being described — the HPA if one is required and the county’s shoreline exemption or permit — or written confirmation from the county and from WDFW that what you are asking for does not need them. If those do not exist, I do not start, and I will help you figure out what to file rather than quietly doing the job and leaving you holding the violation. Filing is the owner’s responsibility and I do not represent anyone at a permit counter. If the honest answer for your project is that it needs a marine contractor and a permit package, I will say that on the first visit and you will not owe me a project.
What that leaves is real work and plenty of it, because the above-water half of a dock is what actually wears out first. Fir and cedar decking on a dock takes more abuse than any deck on land: it is walked on wet, loaded with gear, and it never dries out between October and April. Boards fail at the fasteners and at the ends first, and by the time a board flexes under your heel the fastener has usually been working in a wet hole for a couple of seasons. I replace boards, correct the gapping so the deck actually drains, and use hot-dip galvanized or stainless hardware sized for the exposure. Nothing electroplated goes anywhere near saltwater; it will bleed rust down a new board in one winter and be a smooth pin in three.
Fasteners and corrosion are the whole story on a saltwater dock, and it is worth a paragraph of its own because it is the difference between a repair and an annual habit. Salt spray and immersion cycling attack ordinary galvanized coatings fast, and mixed metals in a wet joint corrode faster still — a stainless screw through a galvanized bracket is a small battery, and the bracket loses. When I open up a railing post or a ladder mount I am looking at what the fastener is doing to the wood and what the two metals are doing to each other, and I standardize the hardware on a given structure rather than adding a third metal to the collection.
Railings, ladders, and cleats are the safety items and they are what I check first. A railing post rotted at the deck line looks fine from ten feet and fails the moment somebody leans on it in a chop. Ladder rungs and their mounting bolts corrode where they alternate wet and dry, which is exactly the zone you grab on the way out of cold water. Cleats pull loose when the backing block behind them has gone soft, and a cleat is only as good as its blocking — replacing the cleat without replacing the block is theater. Where any of this involves the ladder or hardware below the high water line, that is back on the other side of the line and it goes to a marine contractor.
Non-slip is the thing owners underestimate and guests discover. A dock surface here is wet, shaded by the bank for part of the day, and coated in a biological film for most of the winter, which makes it the slickest walking surface on the property by February. Washing is the annual baseline. Beyond that I add adhesive grit strips or grit-embedded finish in the traffic path and on the gangway, where the slope makes it worse, and aluminum nosings where the treads have worn round. I keep it to the walking route rather than coating everything, both because it is cheaper and because a fully coated deck sheds a film of coating into the water eventually, which is not a thing to do on purpose.
The seasonal inspection is probably the most valuable thing on this page for an owner who is not here in the winter. Once a year, ideally in early fall before the weather turns, I walk the structure and write it up with photographs: every soft board, every corroded fastener, every loose railing post, the state of the ladder and cleats, the condition of the gangway hinge and its bearing points, wear at the transition from land to ramp, and specifically a list of anything I can see that belongs to a marine contractor rather than to me. That last list is the point. Below-water problems get found from above the water, and finding them in September is very different from finding them in February. It pairs naturally with a property care plan and with the same fall visit as the gutters.
Two logistics facts that shape what is possible. I run a 16-foot skiff, and 20-foot boards are the hard ceiling for what comes aboard, so if your dock needs longer stock or a real volume of decking, that comes by barge or chartered hauler billed at cost on top of the day rate. And on a waterfront site everything is a tide-window job. Access to a gangway hinge or the landward end of a ramp can be a two-hour opportunity on a given day, which is why I would rather plan a dock visit around the tide table and a specific list than show up with a general intention.

What’s included
- Deck board replacement on docks, ramps, and float decks, with drainage gapping corrected
- Hot-dip galvanized or stainless fasteners appropriate to saltwater exposure, no mixed-metal joints
- Railing, post, and top-rail repair and replacement above the water
- Ladder rung, mount, and hardware replacement above the high water line
- Cleats and chocks re-anchored, with the backing block replaced when it has gone soft
- Gangway and hinge hardware inspection, lubrication, and fastener replacement
- Non-slip treatment: grit strips, grit-embedded finish, and worn tread nosings
- Annual written inspection with photographs, including a list of items for a marine contractor
- Review of the owner’s HPA and county shoreline exemption before any work is scheduled
What it costs
Above-water dock carpentry on San Juan Island runs on the standard $250 minimum visit, which covers two hours, then $85/hour in quarter-hour increments, and lumber and hardware are billed at cost plus pickup time. Washington sales tax applies to the total including labor. Bigger board counts get walked and quoted as a project, because the variable is how much of what you can see is sitting on something that has to be dealt with by somebody else. See the full rate card.
Batch dock work with the tide and with the rest of the property. The efficient version is a fall inspection visit, then one working visit with a defined list and materials already on site, planned around a workable low or high water window depending on what has to be reached. On Orcas, Lopez, and Shaw this runs on the ferry-island day rates, $595 half day and $995 full day on a scheduled island day; outer islands by skiff are $1,295 for a full boat day, no half days. Decking over 20 feet or in quantity comes by barge or chartered hauler at cost, so it is worth ordering once.
Full rate cardCommon questions
Do I need a permit for you to replace deck boards on my dock?
Possibly, and that is the owner’s question to settle before I start. WDFW lists docks, piers, ramps, and floats as project types requiring a Hydraulic Project Approval for repair, modification, and replacement, and says the requirement can extend above the ordinary high water line. San Juan County says repairing an existing dock usually requires an approved exemption from a shoreline permit. I want to see the approvals, or written confirmation from both agencies that your specific work does not need them, before anything gets unscrewed.
What exactly will you not do?
Anything in the water or below the high water line. No pilings, no flotation or float tubs, no anchoring, chain, or cable work, no moving or reconfiguring a ramp or gangway, no bulkheads, no beach or bank work, and no barge-based work. Those are marine contracting and they are permitted work. I do above-water carpentry, hardware, non-slip, and inspection.
Can you tell me what my dock actually needs?
Yes, and that is often the best first purchase. I walk the structure, photograph it, and write up what is soft, what is corroded, what is loose, and what is unsafe, split into two lists: work I can do above the water once the approvals are in hand, and work that belongs to a marine contractor. Early fall is the right time for that, before the weather turns.
Why does the hardware on my dock rust out so fast?
Salt does two things at once. It eats ordinary galvanized coatings far faster than the same fastener would corrode inland, and where two different metals meet in a wet joint the less noble one gives itself up, so a stainless screw through a galvanized bracket quietly destroys the bracket. The fix is hot-dip galvanized or stainless throughout on a given structure, kept consistent rather than mixed.
Photo: Dock deck at low light with a corroded fastener and a soft board end circled, plus the replacement stainless screw and new board alongside.
Shot list: shows the actual failure mode and keeps the frame entirely above the water, which is the point of the page.
Next step
Want this off your list?
Call (360) 317-0203 or send the details and I’ll tell you what it takes.